The contract value was 20 billion dollars. Estimates however believe it is closer to 25 billion. Construction started on 2011. The first unit became operational at 2020, The 4th unit have received its license on November and is expected to operate in the coming weeks. https://www.worldnuclearreport.org/Barakah-UAE-Grid-Connection-of-First-Commercial-Reactor-in-the-Arab-World.html https://www.enec.gov.ae/news/latest-news/barakah-nuclear-energy-plant-unit-1-successfully-connects-to-uae-transmission-grid/ https://www.fanr.gov.ae/en/media-centre/news?g=5345f050-f8b5-4b41-9b3f-f8ebc7797344

Written by 64A4025F46BF15B4F4E605C3C40E36FB2AFB99AED6E2F95AFC838D80BFFEEE02
Participant Details

Original Tweet

Tweet embedding is no longer reliably available, due to the platform's instability (in terms of both technology and policy). If the Tweet still exists, you can view it here: https://twitter.com/foo_bar/status/1732192260429914170

Please note, though, that you may need to have your own Twitter account to access that page. I am currently exploring options for archiving Tweet data in a post-API context.

All Information

  • ID - 1732312465323499734
  • noteId - 1732312465323499734
  • participantId -
  • noteAuthorParticipantId - 64A4025F46BF15B4F4E605C3C40E36FB2AFB99AED6E2F95AFC838D80BFFEEE02 Participant Details
  • createdAtMillis - 1701850451204
  • tweetId - 1732192260429914170
  • classification - MISINFORMED_OR_POTENTIALLY_MISLEADING
  • believable -
  • harmful -
  • validationDifficulty -
  • misleadingOther - 0
  • misleadingFactualError - 1
  • misleadingManipulatedMedia - 0
  • misleadingOutdatedInformation - 1
  • misleadingMissingImportantContext - 0
  • misleadingUnverifiedClaimAsFact - 0
  • misleadingSatire - 0
  • notMisleadingOther - 0
  • notMisleadingFactuallyCorrect - 0
  • notMisleadingOutdatedButNotWhenWritten - 0
  • notMisleadingClearlySatire - 0
  • notMisleadingPersonalOpinion - 0
  • trustworthySources - 0
  • summary
    • The contract value was 20 billion dollars. Estimates however believe it is closer to 25 billion. Construction started on 2011. The first unit became operational at 2020, The 4th unit have received its license on November and is expected to operate in the coming weeks. https://www.worldnuclearreport.org/Barakah-UAE-Grid-Connection-of-First-Commercial-Reactor-in-the-Arab-World.html https://www.enec.gov.ae/news/latest-news/barakah-nuclear-energy-plant-unit-1-successfully-connects-to-uae-transmission-grid/ https://www.fanr.gov.ae/en/media-centre/news?g=5345f050-f8b5-4b41-9b3f-f8ebc7797344

Note Status History

createdAt timestampMillisOfFirstNonNMRStatus firstNonNMRStatus timestampMillisOfCurrentStatus currentStatus timestampMillisOfLatestNonNMRStatus mostRecentNonNMRStatus participantId
2023-12-06 08:14:11 UTC
(1701850451204)
1969-12-31 23:59:59 UTC
(-1)
2023-12-07 04:50:02 UTC
(1701924602413)
NEEDS_MORE_RATINGS 1969-12-31 23:59:59 UTC
(-1)

Note Ratings

rated at rated by
2023-12-06 08:05:50 -0600 Rating Details
2023-12-06 06:41:52 -0600 Rating Details
2023-12-06 06:22:37 -0600 Rating Details
2023-12-06 04:02:16 -0600 Rating Details
2023-12-06 03:10:20 -0600 Rating Details
2023-12-06 03:08:56 -0600 Rating Details
2023-12-06 02:48:45 -0600 Rating Details