Original Note:
The peak shortfall in capacity of 28,345 MW was primarily due to thermal power plant maintenance (4,929 MW) and forced thermal outages (26,280 MW) and to a smaller degree low wind output (2,830 MW), as reported by the Energy Institute of the University of Texas (Fig 2.c). https://energy.utexas.edu/sites/default/files/UTAustin%20%282021%29%20EventsFebruary2021TexasBlackout%2020210714.pdf